VOLVO英文缩写汇总 英文缩写:

PS (Program start)

项目开始

PSC (Program strategy confirmation)

项目策略确定

PTCC (Program Target Compatibility Check

point)

项目目标分解

PTC (Program Target Confirmation)

项目目标确定

PA (Program Approval)

项目批准

LR (Launch Readiness)

投产准备就绪

LS (Launch Sign Off)

投产签收

J1 (Job1)

量产

Use for tooling kick off. 用于开模

Purchasing Related Process/采购相关的流程 Volvo and

suppliers for the commodities. It is for the

commodities

price.

CPA是沃尔沃和供应商之间的关于零件价格的合同。

Tooling order / 模具订单

Tooling order is an order to kick off

suppliers’ tooling

with commercial and engineering

perspectives.

模具订单是沃尔沃从工程和商务两方面来启动供应商的

模具工作。

PPAP

Refer to STA training later

参考后面STA的培训

Purchasing

Drawing related Process/图纸相关流程

V0

1st released version drawing. ESOW1 use it.

Design supplier need release V0 drawing to Volvo

第一版图纸用于ESOW1。设计供应商需要发布V0数据到Volvo 系统

V1

2nd released version drawing. ESOW2 use

it. Design supplier need release

V1 drawing to Volvo

第二版图纸用于ESOW2 。设计供应商需要发布V0数据到Volvo 系统

V2

3rd released version drawing. ESOW3 use it.

Can be used for tooling design.

Design supplier need release V3 drawing to

Volvo

第三版图纸用于ESOW3和模具设计。设计供应商需要发布V2数据到Volvo 系

FDJ

Last released version drawing. Used for

tooling kick off. Design supplier need

release FDJ drawing to Volvo

最终版图纸用于开模。设计供应商需要发布V0 数据到Volvo 系统

Builds/装车活动:

M1 build

M1 build is to verify under body. So under

body related

parts are affected.

M1装车是为了验证下车的设计,所以只有下车体的零

件影响到。

E3/E4 build / E3/E4装车

E3/E4 build is to verify electrical parts’

function (no

dimension requirement). All body electrical

parts are

affected. Chassis and PT electrical parts

are not

affected.

E3/E4装车是为了验证车身电子零件的性能(对几何尺

寸没有要求),车身电子相关零件需要支持该装车。底

盘和动力系统的电气相关的零件不需要支持。

MTO Build (Machine Try Out Build)

MTO build is to verify BIW (body in white)

and body

shop process. All stamping parts are

affected. No any

trim parts are needed. Build will only in

body shop.

Parts must be from job1 tooling. This build

is before

VP

MTO是为了验证白车身和焊装工艺的一次装车,只在焊

装车间进行,只有冲压件会影响到,总装零件不需要支

持。所有零件必须是量产模具制作的。MTO装车 发生在

VP装车之前。

VP build (Verification Prototype Build)

VP build is to verify whole vehicle. All

commodities

affected. Parts must be from job1 tooling.

VP装车验证整车设计,所有零件都需要支持,所有零

件必须是量产模具制作的。

TT build (Tooling Try Build)

TT build is first time to verify the job1

intend process.

All parts must be from job1 tooling and

process. Build

quantity is normally less than 100 cars

TT装车是第一次验证量产工艺的装车,所有零件都必需

从量产意图工艺制作,一般装车数量少于100辆

PP build (Pilot Production Build)

PP build is to verify job1 process with more

quantities

vehicle. All commodities affected. Parts must be

PSW/SOP level.

PP装车是中批量装车验证Job1工艺,所有零件都需要

支持,且要达到PSW/SOP水准。

焊装零件:

PCF Definition/PCF定义

PCF: Body Parts Coordination

PCF: 焊装零件几何尺寸检查

PCF Methods/TPC方法

Use fixtures to simulate standard body then

check the

body parts dimension.

用检具来模拟标准车身,以此来检查焊装零件的几何尺寸。

PCF Plan

Refer to VPP

参考VPP

PCF Related Parts/PCF相关零件

All body parts

所有焊装的零件

总装零件: TPC Definition/TPC定义

TPC: Trim Parts Coordination

TPC: 总装零件几何尺寸检查

TPC Methods/TPC方法

Use fixtures to simulate standard body then

check the

trim parts dimension.

用检具来模拟标准车身,以此来检查总装零件的几何尺寸。

TPC Plan

Refer to VPP

参考VPP